Changes Scheduled for the next seven days - changes are also documented at enhancement.tamu.edu
C1. Replacement of a network router for WERC - February 17.Departmental Changes (CIS resources) for next seven days -
No departmental changes scheduled between February 13 - 20.
Completed Changes -
No changes completed between 5:00 p.m. on February 12 and 5:00 p.m. on February 13.Problems of Major Impact - significant problems are also documented at problem.tamu.edu
No problems reported.Changes Scheduled for the next seven days:
C1. On Saturday, February 17 starting at 7:00 a.m. network communication in the WERC will be disrupted to perform the replacement of a network router. The process is expected to take about 5 hours and should be completed by 12:00 (noon) on February 17. All network connections (except the WERC Open Access Lab) will experience a disruption in communication during the router replacement process.
C2. On Sunday, February 18, starting at 7:30 a.m., maintenance is scheduled to be performed on the batteries that support the cache for the SAN arrays that support the following customers: Evans Library, MLANS and Open Systems. The maintenance is expected to be complete by about 9:00 a.m.Departmental Changes for the next seven days:
No departmental changes scheduled between February 13 - 20.
Completed Changes
No changes completed between 5:00 p.m. on February 12 and 5:00 p.m. on February 13.
No problems reported.
|
Texas A&M University Computing & Information Services Teague Building, Room 322A College Station, TX 77843 |